Jump to content

1,554 posts in this topic

Recommended Posts

Filed: Citizen (apr) Country: Nigeria
Timeline
Posted

Dwheels what e-mail do I send the request for reschedule to?

LagosIV@state.gov

Case Complete to Interview spreadsheet

From now on your VJ Member name will be verified. If the name you put on form to be added to spreadsheet comes up not found, you will not be added to the spreadsheet. If you don't have a timeline you will not be added to the spreadsheet.

Please Please put your VJ member name only. Not nicknames or real names whatever your VJ name is. It's below your profile picture!!

 

Come join the current Interview thread: 

DQ-to-Interview-2023-all-countries

Case Complete to Interview Spreadsheet
Case Complete to Interview Form

 

 

 

ROC I-751
5/21/2018: Filed i751 ROC
6/12/2018: NOA1 Date
3/5/2019: Biometrics Appt
12/28/2019: 18 month Extension has expired
1/9/2020: InfoPass Appt to get stamp in Passport
2/27/2020: Combo Interview (ROC and Citizenship)
3/31/2020: submitted service request for being pass normal processing time
4/7/2020: Card being produced
4/8/2020: Approved
4/10/2020: Card mailed
4/15/2020: 10 year green card received
 
 
N-400
5/21/2019: Filed Online
5/21/2019: NOA1 Date
6/13/2019: Biometrics Appt
2/27/2020: Citizenship Interview
4/7/2020: In queue for Oath Ceremony to be scheduled
6/19/2020: Notice Oath Ceremony scheduled
7/8/2020: Oath Ceremony (Houston)

 

 

 

 

 

 

 

 

Filed: IR-1/CR-1 Visa Country: India
Timeline
Posted

I hope your right!! I still want to see his handsome face on the 21st. That's the only thing that keeps me going some days, his love. Thanks for your support. :).

In India there is a saying that God is sometimes late but he is never unfair...I am sure he is listening to all our prayers and he is going to unite you with your hubby very soon.

IR-1/CR-1 Visa
Service Center : National Benefits Center; Consulate : Mumbai, India; Marriage (if applicable): 2013-07-05
USCIS
I-130 Sent : 2013-07-20; I-130 NOA1 : 2013-07-26; I-130 Transferred to CSC: 2014-01-13; I-130 Approved: 2014-01-22
NVC
NVC Received: 2014-02-03; AOS Bill Shows PAID: 2014-03-19
NVC Case # and IIN Assigned: 2014-03-11; AOS Package Delivered: 2014-03-21;
Submitted/Completed DS-261 online: 2014-03-12; AOS Package Touched: 2014-03-25;
Receive & Pay AOS Bill : 2014-03-13; AOS Package Approved: 2014-04-08
AOS Package Mailed (USPS Priority): 2014-03-18;
IV Bill:
Receive & Pay IV Bill: 2014-03-24; False Checklist for Civil Documents: 2014-04-07
IV Bill Shows PAID: 2014-03-26; Case Completed at NVC: 2014-04-16;
IV Package Mailed (USPS Priority): 2014-03-26; Case Complete Email Received: 2014-04-23
IV Package Received by NVC: 2014-03-31; Interview scheduled: 2014-05-01;
IV Package Touched: 2014-04-03 (still in review); IL Email Received: 2014-05-01
DS-260 Available/Completed/Submitted: 2014-03-27
Consulate: Mumbai
Fingerprinting & Photo: 2014-05-09 Medicals: 2014-05-19
Interview: 2014-06-04 Visa Approved CEAC Website Status "Issued": 2014-06-05
USCIS ELIS Fee Paid: 2014-06-08 Passport w/Visa Received: 2014-06-09
POE (LAX): 2014-07-20 SS# Received: 2014-07-28
Actual GC received 2014-08-30
CA ID Received: 2014-09-02.
First job in USA (yeeeh!!!) starting: 2014-09-22
Taking driving lessons....!!!!

ROC
Application Sent: 2016-04-26
NOA1:2016-04-28
Biometrics: 2016-06-02 (early walk-in on May 31st)

ROC Approval Email and Online Status Change - 2016-11-07
Google Doc for April 2016 filers: https://docs.google.com/spreadsheets/d/12Mb-ALcbwQbYafLj4vFaEMjSGD-wfjtrycs3ul8QlUo/edit?pref=2&pli=1#gid=0

Filed: Citizen (apr) Country: Nigeria
Timeline
Posted

So hubby's interview went ok but we are now in AP. He had everything the NVC requested but apparently there is some other document having to do with marital status that he needed from some government agency there. This is frustrating to me because I went on NVC website under country specific and the only thing that was listed there was about the police clearance.

So he was able to go get this document this afternoon. But he is only allowed to take it back to the embassy tomorrow between 4 and 4:30. Really? A half hour window? And on a Friday no less!! Ugh!!! I'm pretty disgusted right now.

After 14 months of waiting and jumping thru hoops now this!!!!! I can't wait til this bs is over!

And I was thinking we would be so happy and relieved today. And here we are still stressed out!

What more could they want from us? They had our ORIGINAL marriage cert!!!!!!!!!!

The lady at the embassy told him it may still be possible to get the visa next week but they don't do anything quickly there so I'm not holding my breath!

Sorry for the rant. I'm just pi$$ed off! :(

I am sorry for the delay but thats all it is. You can still make that 21st date. So chin up. We don't take defeat here. It is well.

Case Complete to Interview spreadsheet

From now on your VJ Member name will be verified. If the name you put on form to be added to spreadsheet comes up not found, you will not be added to the spreadsheet. If you don't have a timeline you will not be added to the spreadsheet.

Please Please put your VJ member name only. Not nicknames or real names whatever your VJ name is. It's below your profile picture!!

 

Come join the current Interview thread: 

DQ-to-Interview-2023-all-countries

Case Complete to Interview Spreadsheet
Case Complete to Interview Form

 

 

 

ROC I-751
5/21/2018: Filed i751 ROC
6/12/2018: NOA1 Date
3/5/2019: Biometrics Appt
12/28/2019: 18 month Extension has expired
1/9/2020: InfoPass Appt to get stamp in Passport
2/27/2020: Combo Interview (ROC and Citizenship)
3/31/2020: submitted service request for being pass normal processing time
4/7/2020: Card being produced
4/8/2020: Approved
4/10/2020: Card mailed
4/15/2020: 10 year green card received
 
 
N-400
5/21/2019: Filed Online
5/21/2019: NOA1 Date
6/13/2019: Biometrics Appt
2/27/2020: Citizenship Interview
4/7/2020: In queue for Oath Ceremony to be scheduled
6/19/2020: Notice Oath Ceremony scheduled
7/8/2020: Oath Ceremony (Houston)

 

 

 

 

 

 

 

 

Filed: Citizen (pnd) Country: Portugal
Timeline
Posted

Hello again,

(Posting here too so other people can see my comment! ;) )

We had a case complete last May 14th, and we are still waiting for an interview to be scheduled at the Paris embassy. We have been calling everyday since last Wednesday, but no much luck. I was hoping that the delay was "just" due to the holidays / long weekend (embassy was close last Thursday may 28th - and will be close again this upcoming Monday, by the way) and that they would start this week but... nothing yet. I am guessing that we are all looking at the spreadsheet wondering if we are all screwed by PRS or just nobody is "checking back". Pretty sure it is just the immigration process who feels like messing with us a little more. Bad luck from start to the end.

This is ridiculous!! You have been waiting forever. And why so many darn days off? Don't they just get American holidays off? Or do they get the French ones too? Because if that is the case, then I clearly need to work there.

I'm going to track your status and see if you here anything from them. Have you considered calling the embassy themselves?

Dating- 7/29/2008
Engaged- 1/12/2012
Married in Portugal- 8/10/2013
USCIS:
NOA1- 8/15/2013
Transferred to CSC- 2/10/2014
NOA2- 2/19/2014

NVC:
NVC Received Case- 2/27/2014
NVC Case Number- 4/02/2014
AOS Fee Invoiced- 4/04/2014
AOS Fee Paid and AOS Sent- 4/07/2014
IV Fee Invoiced- 4/10/2014

IV Fee Paid- 4/12/2014

AOS Package in NVC System- 4/14/2014

IV Package Sent- 4/17/2014

DS- 260 Available & Completed- 4/18/2014

IV Package in NVC System- 4/24/2014

Checklist for I-864 - 4/29/2014

Checklist for I-864 SENT- 5/1/2014

Checklist for I-864 in NVC System- 5/5/2014

CASE COMPLETE- June 2, 2014 :dance::dancing:(L):luv:
CC Email- 6/9/2014

Interview Date Email- 6/11/ 2014

Medical Exam- 6/24/2014

INTERVIEW DATE- July 22, 2014 at 1PM in Paris, France

POE- August 5, 2014 Finally Home!!!

I am the Petitioner and my husband is the Beneficiary. We are apart, as he is in Portugal and I am in the U.S.

ROC

20 May 2016- I-751 mailed

24 May 2016- ROC received at VSC

6 June 2016- NOA received

10 June 2016- Biometrics Letter received (scheduled for June 22, 2016)

Filed: Citizen (pnd) Country: Portugal
Timeline
Posted

Thanks. I hope so too! I know you feel my pain after all the bs you and your hubby have been through in this process. I thought the worst was over. By the time the interview come you kinda feel like your home free but NOPE!!! Anything can happen!

Hang in there Hun. You are soooo close. You'll get a big ole smooch and hug from him soon.

Dating- 7/29/2008
Engaged- 1/12/2012
Married in Portugal- 8/10/2013
USCIS:
NOA1- 8/15/2013
Transferred to CSC- 2/10/2014
NOA2- 2/19/2014

NVC:
NVC Received Case- 2/27/2014
NVC Case Number- 4/02/2014
AOS Fee Invoiced- 4/04/2014
AOS Fee Paid and AOS Sent- 4/07/2014
IV Fee Invoiced- 4/10/2014

IV Fee Paid- 4/12/2014

AOS Package in NVC System- 4/14/2014

IV Package Sent- 4/17/2014

DS- 260 Available & Completed- 4/18/2014

IV Package in NVC System- 4/24/2014

Checklist for I-864 - 4/29/2014

Checklist for I-864 SENT- 5/1/2014

Checklist for I-864 in NVC System- 5/5/2014

CASE COMPLETE- June 2, 2014 :dance::dancing:(L):luv:
CC Email- 6/9/2014

Interview Date Email- 6/11/ 2014

Medical Exam- 6/24/2014

INTERVIEW DATE- July 22, 2014 at 1PM in Paris, France

POE- August 5, 2014 Finally Home!!!

I am the Petitioner and my husband is the Beneficiary. We are apart, as he is in Portugal and I am in the U.S.

ROC

20 May 2016- I-751 mailed

24 May 2016- ROC received at VSC

6 June 2016- NOA received

10 June 2016- Biometrics Letter received (scheduled for June 22, 2016)

Filed: IR-1/CR-1 Visa Country: Peru
Timeline
Posted

So hubby's interview went ok but we are now in AP. He had everything the NVC requested but apparently there is some other document having to do with marital status that he needed from some government agency there. This is frustrating to me because I went on NVC website under country specific and the only thing that was listed there was about the police clearance.

So he was able to go get this document this afternoon. But he is only allowed to take it back to the embassy tomorrow between 4 and 4:30. Really? A half hour window? And on a Friday no less!! Ugh!!! I'm pretty disgusted right now.

After 14 months of waiting and jumping thru hoops now this!!!!! I can't wait til this bs is over!

And I was thinking we would be so happy and relieved today. And here we are still stressed out!

What more could they want from us? They had our ORIGINAL marriage cert!!!!!!!!!!

The lady at the embassy told him it may still be possible to get the visa next week but they don't do anything quickly there so I'm not holding my breath!

Sorry for the rant. I'm just pi$$ed off! :(

No need to be sorry Stacey, totally understandable. Good news is that is it, that one last piece of paper tomorrow and all those months of waiting will be over! You will see.

Best wishes!!

Our journey to happiness: (click "show" to see our timeline)


05/05/12 - Wedding day!

USCIS

06/07/13 - Mailed I-130
06/10/13 - NOA1
12/19/13 - First text/email for case transfer
12/26/13 - Received hard copy transfer notice: Texas Service Center

01/21/14 - NOA2 Approval text/email
01/25/14 - Received hard copy of approved I-797
01/29/14 - Text/email advising TSC shipped case to DOS

NVC
02/06/14 - NVC received our case file.
03/13/14 - Case number, IIN and BIN assigned
03/17/14 - DS-261 completed. Email Confirmation received
03/18/14 - Received email to pay AOS fee. Invoiced and paid (in process)
03/19/14 - Requested NVC to "join" wife's and daughter's cases
03/20/14 - AOS status "PAID" for wife
03/26/14 - AOS status "PAID" for daughter
03/26/14 - AOS packets sent
03/28/14 - IV available and paid for both wife and daughter (in process)
04/01/14 - IV shows "PAID", DS-260 available
04/05/14 - DS-260 complete and submitted
04/07/14 - Civil docs arrived via DHL from my wife. IV packets sent (Finally!!)
04/14/14 - False checklist for IV packet (wife and daughter)
04/15/14 - Confirmed AOS approved (did not ask for specific approval date) - IV packets in system

04/25/14 - CASE COMPLETE (wife and daughter) :dance:

04/30/14 - Interview scheduled (yay!!)

05/02/14 - Received e-mail with P4 letters

05/07/14 - NVC shipped case files to Lima Embassy via DHL. CEAC status "In transit"

05/09/14 - DHL delivered case files to Embassy. CEAC status "Ready"

Embassy (Lima, PE)

06/09/14 - Medical Exam. 4pm appointment

06/24/14 - Interview appointment @8am Visa approved!!! Bananeyessss.gifBananezorro.gif

06/25/14 - CEAC status "Issued"

06/28/14 - Visa in hand

08/05/14 - POE !! smiley-happy093.gif

Filed: Citizen (pnd) Country: Sri Lanka
Timeline
Posted

Spouse collected the passport and the documents from embassy..... soo ready to come in..... :dance: :dance: :dance:

Saylin and dwheels76,

Very appreciated for helping us being there! You two deserve BIG Thank YOU!!! (F) (F) (F)

I-130 Track:

Feb 19, 2013: I-130 Sent

Feb 19, 2013: Priority Date

Feb 22, 2013: NOA1 Received

Sep 04, 2013: RFE received

Oct 04, 2013: RFE response

Dec 05, 2013: NOA2 Approved

Dec 12, 2013: NOA2 Hard copy received

NVC Track:

Dec 17, 2013: NVC received file

Jan 10, 2014: NVC Case # and IIN assigned

Jan 17, 2014: Email to pay AOS & IV fee

Jan 17, 2014: AOS & IV invoice available

Jan 21, 2014: AOS & IV fees paid

Jan 23, 2014: AOS & IV show as "PAID"

Jan 23, 2014: DS260 available & completed

Jan 30, 2014: AOS & IV packet sent (my paralegal delayed this)

Feb 04, 2014: AOS & IV entered in to the system

Feb 19, 2014: Second IV packet delivered to NVC (Entered to the system on 20th)

Feb 26, 2014: Check list for AOS

Feb 27, 2014: Response to AOS checklist sent - New AOS

Mar 04, 2014: AOS checklist response entered to the system

Mar 13, 2014: False checklist for AOS checklist response (IV pkts were reviewed/Approved)

Mar 18, 2014: Case Completed (As per call to NVC on March 19th)

Apr 02, 2014: Interview scheduled for May 22nd

May 22, 2014: Interview............ Visa Approved!!!

Jun 05, 2014: PP & docs collected from embassy

Jun 22, 2014: POE

Filed: IR-1/CR-1 Visa Country: Morocco
Timeline
Posted

My petition's status changed today from "In Transit" to "Ready".

I will be floading the consulat in Casablanca with email to try and get an earlier interview date.

I really hope they allow us if they have open spots

11/17/2016: Got engaged
11/28/2016: I-130 sent to Chicago IL lock box
01/12/2016: NOA1

Posted

Filled out the form

I haven't been on VJ for a bit because it was making me so anxious about our case. Plus the new baby and all the expenses. I'm slowly losing my mind.

But we're almost done. I just hope that nothing goes wrong during the interview.

Hi..when did you get your interview date? I got my CC last May 28.. still waiting for my interview schedule..

TIA

USCIS STAGE:

August 17, 2013 - I-130 sent

August 22, 2013 - noa1

November 22, 2013 - tranferred to TSC

December 16, 2013 - approved

December 19, 2013 - noa2 hardcopy

January 09, 2014 - shipped to NVC

NVC STAGE:

January 17, 2014 - case received

February 24, 2014 - case number received

February 25, 2014 - IIN and BIN received

March 01, 2014 - ds 261 completed

March 05, 2014 - aos invoice and paid (in process)

March 07, 2014 - aos shows paid

March 22, 2014 - iv bill paid (in process)

March 25, 2014 - iv bill shows paid

March 25, 2014 - ds260 completed

March 26,2014 - iv package send to nvc

March 31, 2014 - iv package arrived at NVC 12:05pm (Gary S. Peters - signatory)

April 01, 2014 - aos send (certified mail)

April 03, 2014 - iv docs logged into the system (according to olivia)

April 05, 2014 - aos arrived at nvc but business closed. waiting them (usps) to redeliver it on Monday.

April 07, 2014 - aos finally arrived at NVC 11:50am

April 09, 2014 - aos logged into the the system (according to olivia)

April 24, 2014 - aos checklist (thru phone call)

April 25, 2014 - aos checklist email received

April 29, 2014 - checklist responce

May 02, 2014 - arrived at nvc signed by B. Standish

May 05, 2014 - checklist responce log into the system

May 28, 2014 - CASE COMPLETE .. Thank God

June 04, 2014 - received email (case complete)

June 09-10, 2014 - done advance medical

June 11, 2014 - interview schedule (email received)

July 02, 2014 - interview (APPROVED) Thank you Lord;)

Filed: IR-1/CR-1 Visa Country: Thailand
Timeline
Posted

So hubby's interview went ok but we are now in AP. He had everything the NVC requested but apparently there is some other document having to do with marital status that he needed from some government agency there. This is frustrating to me because I went on NVC website under country specific and the only thing that was listed there was about the police clearance.

So he was able to go get this document this afternoon. But he is only allowed to take it back to the embassy tomorrow between 4 and 4:30. Really? A half hour window? And on a Friday no less!! Ugh!!! I'm pretty disgusted right now.

After 14 months of waiting and jumping thru hoops now this!!!!! I can't wait til this bs is over!

And I was thinking we would be so happy and relieved today. And here we are still stressed out!

What more could they want from us? They had our ORIGINAL marriage cert!!!!!!!!!!

The lady at the embassy told him it may still be possible to get the visa next week but they don't do anything quickly there so I'm not holding my breath!

Sorry for the rant. I'm just pi$$ed off!

I am the same, they asked for some docs from the petitioner (my husband). And the CO was a bit rude and confusing. And they gave me another interview in a private room. I am so so so sad and my husband could not sleep. They gave as checlist e.g. I need a new passport bec it will expire in 7 months, civil docs from my husband and more proof about our relationship and we submitted everything to them. What else do they need. I think the CO was in a bad mood. the other woman next to me was the same AP. Are there any possibility that we would be denied? Please help.

(F) 2013-01-03 - Got married (F) (L) (L) (L)

USCIS

NVC

2013-01-21 - Sent i-130 2014-01-17 - NVC received 2014-04-30 - email for case complete received (got early in the morning)

2013-02-22 - NOA1 2014-02-28 - NVC case number assigned 2014-04-30 - Interview scheduled (by phone in the afternoon)

2013-12-10 got RFE 2014-03-03 - AOS (I-864) and IV bill paid 2014-05-02 - IL received by email

2013-12-23 RFE sent 2014-03-06 - Sent I-864(AOS) Package 2014-05-03 - Case in Transit (checked from ceac tracking)

2014-01-03 Approved 2014-03-07 - DS-260 completed online 2014-05-09 - Case Ready (Ceac tracking)

2014-01-21 - NOA2 2014-03-24 - Received checklist for IV (civil docs)

2014-03-27 - Received checklist for AOS

2014-04-01 - Sent AOS package and original civil docs by our attorney via regular mail (respond to checklist)

2014-04-07 - Received AOS and civil docs package by NVC

2014-04-09 - AOS and civil docs package (checklist) by NVC logged in the system

2014-04-23 - Case completed Consulate

2014-05-05 - Medical done

2014-06-06 - Interview (AP received 221g white form for additional documents, letter from my husband answering the CO's questions in the form ) and proofs (e.g. emails, pictures, call logs, etc which we already submitted during the interview but still I added more evidence such as our FB Private Messages, money transfer receipts and a letter from my husband's bishop to prove that our marriage is real)

2014-06-17 - Status updated still AP

2014-06-18 - Status updated still AP - (the US Emb. received the doc.) 2014-06-19 - Status updated still AP

2014-06-26 - Status updated still AP 2014-07-01 - Status updated still AP - (my husband wrote an email to the CO and he got a reply. - said under consideration)

2014-07-16 - Status updated still AP - (the house of rep. sent them an email and the US Embassy replied to him/her)

2014-07- 18 - USEM received more evidence we sent (Western Union - money transfer receipt).

2014-07- 20 - Status updated still AP (confused bec it is Sunday on the 20th July, maybe scanned the additional docs sent to them)

2014-07- 21 - Status updated still AP 2014-07- 23 - My husband went to the house of Senate and they attended to him right away.

2014-07- 24 - The asst. at the senate responded immediately and contacted the USEM.

2014-07- 28 - Status updated still AP (received an email from the USEM, 1. Applicant, your case is ready to be issued, but your passport #********** needs to be cancelled first & returned to our office at your earliest convenience. Please contact visasbkki@state.gov to pick up your old passport to complete this step.)

2014-07- 28 - Cancelled my old passport and sent them to the USEM.

2014-07- 30 - The embassy received my 2 passports (old and new) 2014-07- 31 - Status updated still AP (Maybe scanned my mail)

2014-08- 08 - Status updated "READY"

2014-08- 13 - Status updated still "READY" I sent them an email re the ready status. Aug. 11 & 12 National holiday USEM closed.

2014-08- 14 - Status updated still "READY" I received an email from the USEM,We have received your said documents. Please be informed that your visa has now been approved. We are working with the preparation of your visa package and will mail it to the applicant address on GSS profile which takes approximately 7-10 days. Applicant should refrain from making any irrevocable travel arrangements until he/she receives.<p>

2014-08- 18 - Visa in-hand

2014-09-07 arrived Atlanta airport

Filed: IR-1/CR-1 Visa Country: India
Timeline
Posted

how to check my case status on CEAC site?

I-130 USCIS

NOA1: 08/15/2013

NOA1 Hardcopy: 08/22/2013

Case transferred to CSC: 02/10/2014

Case transfer Hardcopy: 02/19/2014

NOA2: 03/05/2014

NOA2 Hardcopy: 03/10/2014

NVC:

Case arrived at NVC: 03/13/2014

Case number,IIN,BIN assigned and email id given: 04/14/2014

DS261 Available and Completed: 04/18/2014

DS261 accepted and received instruction: 04/21/2014

AOS fee paid and Payment status is "IN PROCESS": 04/21/2014

AOS Payment status shows PAID: 04/24/2014

AOS mailed to NVC: 04/24/2014

IV fee paid and payment status shows " IN PROCESS" : 04/25/2014

IV fee payment status shows PAID: 04/29/2014

Approved IV packet and DS260: 05/20/2014

Interview Date(Got from NVC by call on 05/30/2014): 07/15/2014

Received Interview Letter from NVC by email: 06/02/2014.

Biometrics done at VAC,Chennai: 06/16/2014

Medicals done at Apollo,Chennai: 06/17/2014

VISA APPROVED at Mumbai embassy: 07/15/2014

VISA Pick up at Chennai VFC: 07/18/2014

Port Of Entry: 9/4/2014

SSN Arrived: 10/6/2014

Green Card Arrived: 10/22/2014

Case Complete: 05/27/2014

 

Removal of Conditional - Joint Waiver/Divorced

 

Green Card Expired: 9/04/2016

NOA Date: 7/13/2016

Biometric Date: 8/2/2016

I-551 Samping: 7/7/2017 at Dallas Field Office

I-751 Approved: 10/07/2017 (USCIS status: New card is being produced)

New Green Card Received:  

 

Filed: IR-1/CR-1 Visa Country: India
Timeline
Posted

This is an advance warning for those with interviews coming up in the coming days and weeks. If your 2013 tax was filed as Single, there is a very high probability of your application being put into AP until you (your petitioner) fix that error. So it is a much better idea to submit a 1040X and change your filing status to anything but Single (MFS, HOH, MFJ ) and carry a copy of this with you along with your 2013 Tax Return.

IR-1/CR-1 Visa
Service Center : National Benefits Center; Consulate : Mumbai, India; Marriage (if applicable): 2013-07-05
USCIS
I-130 Sent : 2013-07-20; I-130 NOA1 : 2013-07-26; I-130 Transferred to CSC: 2014-01-13; I-130 Approved: 2014-01-22
NVC
NVC Received: 2014-02-03; AOS Bill Shows PAID: 2014-03-19
NVC Case # and IIN Assigned: 2014-03-11; AOS Package Delivered: 2014-03-21;
Submitted/Completed DS-261 online: 2014-03-12; AOS Package Touched: 2014-03-25;
Receive & Pay AOS Bill : 2014-03-13; AOS Package Approved: 2014-04-08
AOS Package Mailed (USPS Priority): 2014-03-18;
IV Bill:
Receive & Pay IV Bill: 2014-03-24; False Checklist for Civil Documents: 2014-04-07
IV Bill Shows PAID: 2014-03-26; Case Completed at NVC: 2014-04-16;
IV Package Mailed (USPS Priority): 2014-03-26; Case Complete Email Received: 2014-04-23
IV Package Received by NVC: 2014-03-31; Interview scheduled: 2014-05-01;
IV Package Touched: 2014-04-03 (still in review); IL Email Received: 2014-05-01
DS-260 Available/Completed/Submitted: 2014-03-27
Consulate: Mumbai
Fingerprinting & Photo: 2014-05-09 Medicals: 2014-05-19
Interview: 2014-06-04 Visa Approved CEAC Website Status "Issued": 2014-06-05
USCIS ELIS Fee Paid: 2014-06-08 Passport w/Visa Received: 2014-06-09
POE (LAX): 2014-07-20 SS# Received: 2014-07-28
Actual GC received 2014-08-30
CA ID Received: 2014-09-02.
First job in USA (yeeeh!!!) starting: 2014-09-22
Taking driving lessons....!!!!

ROC
Application Sent: 2016-04-26
NOA1:2016-04-28
Biometrics: 2016-06-02 (early walk-in on May 31st)

ROC Approval Email and Online Status Change - 2016-11-07
Google Doc for April 2016 filers: https://docs.google.com/spreadsheets/d/12Mb-ALcbwQbYafLj4vFaEMjSGD-wfjtrycs3ul8QlUo/edit?pref=2&pli=1#gid=0

Filed: IR-1/CR-1 Visa Country: India
Timeline
Posted

how to check my case status on CEAC site?

Here is the link: https://ceac.state.gov/CEACStatTracker/Status.aspx?eQs=o/iS8zDpeAKjMWCuebHqOw==

Enter your case # to get the status.

IR-1/CR-1 Visa
Service Center : National Benefits Center; Consulate : Mumbai, India; Marriage (if applicable): 2013-07-05
USCIS
I-130 Sent : 2013-07-20; I-130 NOA1 : 2013-07-26; I-130 Transferred to CSC: 2014-01-13; I-130 Approved: 2014-01-22
NVC
NVC Received: 2014-02-03; AOS Bill Shows PAID: 2014-03-19
NVC Case # and IIN Assigned: 2014-03-11; AOS Package Delivered: 2014-03-21;
Submitted/Completed DS-261 online: 2014-03-12; AOS Package Touched: 2014-03-25;
Receive & Pay AOS Bill : 2014-03-13; AOS Package Approved: 2014-04-08
AOS Package Mailed (USPS Priority): 2014-03-18;
IV Bill:
Receive & Pay IV Bill: 2014-03-24; False Checklist for Civil Documents: 2014-04-07
IV Bill Shows PAID: 2014-03-26; Case Completed at NVC: 2014-04-16;
IV Package Mailed (USPS Priority): 2014-03-26; Case Complete Email Received: 2014-04-23
IV Package Received by NVC: 2014-03-31; Interview scheduled: 2014-05-01;
IV Package Touched: 2014-04-03 (still in review); IL Email Received: 2014-05-01
DS-260 Available/Completed/Submitted: 2014-03-27
Consulate: Mumbai
Fingerprinting & Photo: 2014-05-09 Medicals: 2014-05-19
Interview: 2014-06-04 Visa Approved CEAC Website Status "Issued": 2014-06-05
USCIS ELIS Fee Paid: 2014-06-08 Passport w/Visa Received: 2014-06-09
POE (LAX): 2014-07-20 SS# Received: 2014-07-28
Actual GC received 2014-08-30
CA ID Received: 2014-09-02.
First job in USA (yeeeh!!!) starting: 2014-09-22
Taking driving lessons....!!!!

ROC
Application Sent: 2016-04-26
NOA1:2016-04-28
Biometrics: 2016-06-02 (early walk-in on May 31st)

ROC Approval Email and Online Status Change - 2016-11-07
Google Doc for April 2016 filers: https://docs.google.com/spreadsheets/d/12Mb-ALcbwQbYafLj4vFaEMjSGD-wfjtrycs3ul8QlUo/edit?pref=2&pli=1#gid=0

Filed: IR-1/CR-1 Visa Country: Morocco
Timeline
Posted

I just called the Consulat in Casablanca and actually spoke to 2 people. They both asked me to send an email requesting the change of interview schedule to June and they will get back to me as soon as they can.

I really have a good feeling about this! Hopefully it works and we get an earlier interview!!!!!!!!!!!!!!

11/17/2016: Got engaged
11/28/2016: I-130 sent to Chicago IL lock box
01/12/2016: NOA1

Filed: IR-1/CR-1 Visa Country: India
Timeline
Posted

Here is the link: https://ceac.state.gov/CEACStatTracker/Status.aspx?eQs=o/iS8zDpeAKjMWCuebHqOw==

Enter your case # to get the status.

Hi bkghosh,

In the embassy did they restrict any stationary items like files and folders. Would I be able to carry a wedding album in?

Regards

cdss

USCIS

5/11/2013: NOA 1-130

2/21/2014: I-130 Approved

NVC Stage

3/17/2014: NVC received case

4/16/2014: NVC case number assigned

4/23/2014: DS-261 Submitted Online

4/24/2014: AOS bill generated and paid

4/29/2014: AOS bill shows PAID

4/30/2014: IV bill generated and paid

5/2/2014: NVC receives AOS Package

5/5/2014: IV bill shows PAID

5/7/2014: NVC receives IV Package

5/8/2014: DS-260 Completed and submitted

5/30/2014: Case Complete !!

6/5/2014: CC Email Received

6/11/2014: Interview Date Scheduled

7/17/2014: Interview Date at Mumbai

 
Didn't find the answer you were looking for? Ask our VJ Immigration Lawyers.
Guest
This topic is now closed to further replies.
- Back to Top -

Important Disclaimer: Please read carefully the Visajourney.com Terms of Service. If you do not agree to the Terms of Service you should not access or view any page (including this page) on VisaJourney.com. Answers and comments provided on Visajourney.com Forums are general information, and are not intended to substitute for informed professional medical, psychiatric, psychological, tax, legal, investment, accounting, or other professional advice. Visajourney.com does not endorse, and expressly disclaims liability for any product, manufacturer, distributor, service or service provider mentioned or any opinion expressed in answers or comments. VisaJourney.com does not condone immigration fraud in any way, shape or manner. VisaJourney.com recommends that if any member or user knows directly of someone involved in fraudulent or illegal activity, that they report such activity directly to the Department of Homeland Security, Immigration and Customs Enforcement. You can contact ICE via email at Immigration.Reply@dhs.gov or you can telephone ICE at 1-866-347-2423. All reported threads/posts containing reference to immigration fraud or illegal activities will be removed from this board. If you feel that you have found inappropriate content, please let us know by contacting us here with a url link to that content. Thank you.
×
×
  • Create New...