https://egov.uscis.gov/cris/processingTimesDisplay.do

they have updated USCIS website, but for CSC- same date 18th July-2012

so my question is, does it means that in one month , they did not approve I-129F, but on the other hand some of from

July they approved.............whats going on.................

event.png

event.png

192230.gif

Link to comment
Share on other sites

Filed: AOS (pnd) Country: Jamaica
Timeline

im confused as well, two months later and they are working on the same date... so disheartening.. a process that was suppose to take 5 or 6 months tops may take close to a year.. im just under 4 months in, and truly believe theres another 5 or 6 months left for us :(

09/27/2012 Engaged in Jamaica

12/4/2012 Texas Service Center received paperwork USPS delivery conf

12/5/2012 Touched

12/7/2012 Check cashed

12/7/2012 NOA1 sent email and SMS text..forwarded to California Service Center

12/11/2012 Website updated initial review

12/13/2012 NOA1 hardcopy received

04/16/2013 Website updated*** APPROVED!!

04/19/2013 NOA2 Hardcopy recieved

05/30/2013 medical appt

06/13/2013 interview day!! ---APPROVED!!!!

Ceac website: two weeks in "ready "

Ceac website: one week in "AP"

Ceac website: one week back in "ready"

07/10/2013 ceac website -visa:issued..no airbill number

07/15/2013 still no visa kng embassy is ran by incompetent baboons

07/17/2013 notified visa w/dhl

07/18/2013 fiance picked up visa

08/04/2013 POE

08/08/2013 Wedding Day

08/26/2013 mailed AOS,EAD,AP paperwork

08/28/2013 tracking conf papers delivered

09/04/2013 3 txt msgs recvd with cases #s

09/06/2013 check cashed

09/09/2013 recvd all (3) Noa1 hardcopies

10/01/2013 Biometrics appt (hoping to do a walk in)--successful walk in done 9-16

10/31/2013 EAD/AP approved

11/09/2013 EAD/AP in hand!

01/27/2013 Green Card in production!!

01/31/2013 Received a "welcome to America "letter

02/05/2014 GREEN CARD IN HAND!!

Link to comment
Share on other sites

im confused as well, two months later and they are working on the same date... so disheartening.. a process that was suppose to take 5 or 6 months tops may take close to a year.. im just under 4 months in, and truly believe theres another 5 or 6 months left for us :(

It's only a month according to USCIS. Their update only accounts for the month of January. As has been noted on here numerous times, CSC pretty much stopped doing I-129F applications because they were swamped with DACA. VSC had a similar problems that slowed them to a crawl as well. VSC moved DACA cases to Nebraska something like 6 weeks ago or so, and they quickly caught back up. CSC just moved DACA cases this month, and the hope is that they will also catch back up soon.

FILE FOR K-1 Adjustment of Status Removal of Conditions

January 31.2010 - Met Online April 10, 2014 - Mailed in I-485 + I-765 March 19, 2016 - Mailed I-751 to CSC

February 20, 2011 - Met in Person April 14, 2014 - Forms arrived at Chicago Lockbox March 23, 2016 - I-751 arrived at CSC

July 28, 2012 - Engaged April 17, 2014 - Acceptance email arrived stating case forwarded to NBC March 23, 2016 - NOA1 Date (received March 28)

February 5, 2013 - Mailed I-129F to Lewisville, TX April 27, 2014 - Received letter for Biometrics appointment April 20, 2016 - Biometrics scheduled (incomplete due to dry cracked skin)

February 6, 2013 - USPS Receipt/Delivered I-129F April 28, 2014 - Received Acceptance NOA1 hard copies for AOS and EAD May 13, 2016 - Walk in Biometrics Completed

February 8, 2013 - NOA1 Notice Date May 12, 2014 - Biometrics Appointment Done September 27, 2016 - ROC Approved (Checked status via website w/receipt #)

February 11, 2013 - Bank shows check cashed today May 15, 2014 - Interview Schedule Letter (received May 17, 2014) October 6, 2016 - Card Arrived

February 11, 2013 - E-Mail Notification of Case Acceptance and June 5, 2014 - Interview Scheduled at Local office 8:15 a.m.

Case Number (Routed to California Service Center) June 11, 2014 - USCIS Status updated to show Greencard in the mail

February 12, 2013 - E Mail Notification of Alien Registration Number Change w/USPS tracking showing it scheduled to arrive

February 15, 2013 - Hard Copy NOA1 received June 14, 2014

June 5, 2013 - Email notice of RFE June 13, 2014 - GreenCard arrived

June 6, 2013 - RFE postmarked

June 10, 2013 - RFE arrived in the mail

June 11, 2013 - RFE mailed back Express USPS

June 12, 2013 - RFE received @ CSC / USCIS website updated to reflect this

June 20, 2013 - I-129F Approved

June 24, 2013 - NOA2 Hard Copy Received

June 28, 2013 - NVC Assigned Case Number

July 2, 2013 - NVC shipped case to London

July 9, 2013 - London Received Case File

July 13, 2013 - Packet 3 Instructions Received

July 17, 2013 - Packet 3 Forms Mailed (Except DS-2001)

July 30, 2013 - DS-2001 sent (arrived July 31)

July 30, 2013 - Medical Scheduled (and completed w/no issues)

August 5th - Medical Results Logged in

August 8th - DS-2001 Logged in

August 20, 2013 - Interview Date Set

September 17, 2013 - Interview at 8:00 a.m. (APPROVED)

Waiting for VISA...

September 25, 2013 - Visa Delivered

October 8, 2013 - POE Las Vegas, NV

October 11, 2013 - Married

October 13th - HOME

Link to comment
Share on other sites

Filed: K-1 Visa Country: Philippines
Timeline
However, if that office is taking longer than our processing goal to handle the form type in question, you will see the filing date (e.g., "April 10, 2003") of the last case we processed on the date the website chart was last updated. The charts are updated on or about the 15th day of each month.

So what this claims, is that the last case they processed was July 18, on March 22.

The problem with that is that it is totally not true. They have processed cases beyond that date. That is very clear from Igor's list.

Why can't they just be up front and give an honest explanation of what is going on, instead of hiding by publishing dates and explanations that are false?

Link to comment
Share on other sites

So what this claims, is that the last case they processed was July 18, on March 22.

The problem with that is that it is totally not true. They have processed cases beyond that date. That is very clear from Igor's list.

Why can't they just be up front and give an honest explanation of what is going on, instead of hiding by publishing dates and explanations that are false?

Actually if you look at the processing times page, it states that it is current through January 31, not current through the day it was updated

Edited by UK-USA-K1
FILE FOR K-1 Adjustment of Status Removal of Conditions

January 31.2010 - Met Online April 10, 2014 - Mailed in I-485 + I-765 March 19, 2016 - Mailed I-751 to CSC

February 20, 2011 - Met in Person April 14, 2014 - Forms arrived at Chicago Lockbox March 23, 2016 - I-751 arrived at CSC

July 28, 2012 - Engaged April 17, 2014 - Acceptance email arrived stating case forwarded to NBC March 23, 2016 - NOA1 Date (received March 28)

February 5, 2013 - Mailed I-129F to Lewisville, TX April 27, 2014 - Received letter for Biometrics appointment April 20, 2016 - Biometrics scheduled (incomplete due to dry cracked skin)

February 6, 2013 - USPS Receipt/Delivered I-129F April 28, 2014 - Received Acceptance NOA1 hard copies for AOS and EAD May 13, 2016 - Walk in Biometrics Completed

February 8, 2013 - NOA1 Notice Date May 12, 2014 - Biometrics Appointment Done September 27, 2016 - ROC Approved (Checked status via website w/receipt #)

February 11, 2013 - Bank shows check cashed today May 15, 2014 - Interview Schedule Letter (received May 17, 2014) October 6, 2016 - Card Arrived

February 11, 2013 - E-Mail Notification of Case Acceptance and June 5, 2014 - Interview Scheduled at Local office 8:15 a.m.

Case Number (Routed to California Service Center) June 11, 2014 - USCIS Status updated to show Greencard in the mail

February 12, 2013 - E Mail Notification of Alien Registration Number Change w/USPS tracking showing it scheduled to arrive

February 15, 2013 - Hard Copy NOA1 received June 14, 2014

June 5, 2013 - Email notice of RFE June 13, 2014 - GreenCard arrived

June 6, 2013 - RFE postmarked

June 10, 2013 - RFE arrived in the mail

June 11, 2013 - RFE mailed back Express USPS

June 12, 2013 - RFE received @ CSC / USCIS website updated to reflect this

June 20, 2013 - I-129F Approved

June 24, 2013 - NOA2 Hard Copy Received

June 28, 2013 - NVC Assigned Case Number

July 2, 2013 - NVC shipped case to London

July 9, 2013 - London Received Case File

July 13, 2013 - Packet 3 Instructions Received

July 17, 2013 - Packet 3 Forms Mailed (Except DS-2001)

July 30, 2013 - DS-2001 sent (arrived July 31)

July 30, 2013 - Medical Scheduled (and completed w/no issues)

August 5th - Medical Results Logged in

August 8th - DS-2001 Logged in

August 20, 2013 - Interview Date Set

September 17, 2013 - Interview at 8:00 a.m. (APPROVED)

Waiting for VISA...

September 25, 2013 - Visa Delivered

October 8, 2013 - POE Las Vegas, NV

October 11, 2013 - Married

October 13th - HOME

Link to comment
Share on other sites

Filed: K-1 Visa Country: Philippines
Timeline

Actually if you look at the processing times page, it states that it is current through January 31, not current through the day it was updated

Yes, but that conflicts with the statement on the page that I quoted, "on the date the website was updated" to me means March 22.

Link to comment
Share on other sites

Filed: Citizen (apr) Country: Denmark
Timeline

So what this claims, is that the last case they processed was July 18, on March 22.

The problem with that is that it is totally not true. They have processed cases beyond that date. That is very clear from Igor's list.

Why can't they just be up front and give an honest explanation of what is going on, instead of hiding by publishing dates and explanations that are false?

That date is more of a cut off date, like they've processed 98% (I'm guessing) application processed before then and if you were earlier then you can file a service request.

3/2/18  E-filed N-400 under 5 year rule

3/26/18 Biometrics

7/2019-12/2019 (Yes, 16- 21 months) Estimated time to interview MSP office.

 

Link to comment
Share on other sites

Yes, but that conflicts with the statement on the page that I quoted, "on the date the website was updated" to me means March 22.

I'm not sure I see what you see. This is what I see on the CSC processing times page:

USCIS Processing Time Information for our

California Service Center

Posted: March 22, 2013

Instructions on Using the Table

Below is a chart that shows the Form Number, Form Name and Processing Times for all of the forms that are processed at that office. (Note that not all offices process all types of applications and petitions.)

Find the particular form number (in the left column) or form name (in the center column) in which you are interested. In the right column you will find either a timeframe in months or an exact date.

If the office is processing a particular type of application in less time than our processing goal, you will see the processing times expressed in months (for example, if the office is processing naturalization applications in less than our 5 month goal, the processing time will state "Five Months"). However, if that office is taking longer than our processing goal to handle the form type in question, you will see the filing date (e.g., "April 10, 2003") of the last case we processed on the date the website chart was last updated. The charts are updated on or about the 15th day of each month.

IMPORTANT: If your receipt notice date is earlier then the processing date shown, we suggest you call our USCIS Customer Service Office at 1-800-375-5283 for assistance.

Please note that the processing times listed below for Form Number I-765 category ©(8), based on a pending asylum application, only applies to an initial filing. The processing time for a renewal I-765 category ©(8) is 3 Months.

The 90-day period for reviewing Form I-765 filed together with Form I-821D begins if and when USCIS decides whether to defer action in your case.

We offer a variety of services after you file. For example, for most kinds of cases you can check the status of your case online.

Field Office Processing Dates for California Service Center as of: January 31, 2013

Perhaps you are confusing the difference between date posted and date updated. It's not the same. This was posted on March 22, but it was updated as of January 31.

Edited by UK-USA-K1
FILE FOR K-1 Adjustment of Status Removal of Conditions

January 31.2010 - Met Online April 10, 2014 - Mailed in I-485 + I-765 March 19, 2016 - Mailed I-751 to CSC

February 20, 2011 - Met in Person April 14, 2014 - Forms arrived at Chicago Lockbox March 23, 2016 - I-751 arrived at CSC

July 28, 2012 - Engaged April 17, 2014 - Acceptance email arrived stating case forwarded to NBC March 23, 2016 - NOA1 Date (received March 28)

February 5, 2013 - Mailed I-129F to Lewisville, TX April 27, 2014 - Received letter for Biometrics appointment April 20, 2016 - Biometrics scheduled (incomplete due to dry cracked skin)

February 6, 2013 - USPS Receipt/Delivered I-129F April 28, 2014 - Received Acceptance NOA1 hard copies for AOS and EAD May 13, 2016 - Walk in Biometrics Completed

February 8, 2013 - NOA1 Notice Date May 12, 2014 - Biometrics Appointment Done September 27, 2016 - ROC Approved (Checked status via website w/receipt #)

February 11, 2013 - Bank shows check cashed today May 15, 2014 - Interview Schedule Letter (received May 17, 2014) October 6, 2016 - Card Arrived

February 11, 2013 - E-Mail Notification of Case Acceptance and June 5, 2014 - Interview Scheduled at Local office 8:15 a.m.

Case Number (Routed to California Service Center) June 11, 2014 - USCIS Status updated to show Greencard in the mail

February 12, 2013 - E Mail Notification of Alien Registration Number Change w/USPS tracking showing it scheduled to arrive

February 15, 2013 - Hard Copy NOA1 received June 14, 2014

June 5, 2013 - Email notice of RFE June 13, 2014 - GreenCard arrived

June 6, 2013 - RFE postmarked

June 10, 2013 - RFE arrived in the mail

June 11, 2013 - RFE mailed back Express USPS

June 12, 2013 - RFE received @ CSC / USCIS website updated to reflect this

June 20, 2013 - I-129F Approved

June 24, 2013 - NOA2 Hard Copy Received

June 28, 2013 - NVC Assigned Case Number

July 2, 2013 - NVC shipped case to London

July 9, 2013 - London Received Case File

July 13, 2013 - Packet 3 Instructions Received

July 17, 2013 - Packet 3 Forms Mailed (Except DS-2001)

July 30, 2013 - DS-2001 sent (arrived July 31)

July 30, 2013 - Medical Scheduled (and completed w/no issues)

August 5th - Medical Results Logged in

August 8th - DS-2001 Logged in

August 20, 2013 - Interview Date Set

September 17, 2013 - Interview at 8:00 a.m. (APPROVED)

Waiting for VISA...

September 25, 2013 - Visa Delivered

October 8, 2013 - POE Las Vegas, NV

October 11, 2013 - Married

October 13th - HOME

Link to comment
Share on other sites

Filed: K-1 Visa Country: Philippines
Timeline

This is what I am referring to:

If the office is processing a particular type of application in less time than our processing goal, you will see the processing times expressed in months (for example, if the office is processing naturalization applications in less than our 5 month goal, the processing time will state "Five Months"). However, if that office is taking longer than our processing goal to handle the form type in question, you will see the filing date (e.g., "April 10, 2003") of the last case we processed on the date the website chart was last updated. The charts are updated on or about the 15th day of each month
Link to comment
Share on other sites

This is what I am referring to:

Exactly, last updated, not last posted. It was POSTED on March 22. The update is for January 31. They haven't updated the information since that date. We call this updating the website when we talk about it, but technically, it's just the January 31 update being posted in March. In April they will have the update through February etc.

FILE FOR K-1 Adjustment of Status Removal of Conditions

January 31.2010 - Met Online April 10, 2014 - Mailed in I-485 + I-765 March 19, 2016 - Mailed I-751 to CSC

February 20, 2011 - Met in Person April 14, 2014 - Forms arrived at Chicago Lockbox March 23, 2016 - I-751 arrived at CSC

July 28, 2012 - Engaged April 17, 2014 - Acceptance email arrived stating case forwarded to NBC March 23, 2016 - NOA1 Date (received March 28)

February 5, 2013 - Mailed I-129F to Lewisville, TX April 27, 2014 - Received letter for Biometrics appointment April 20, 2016 - Biometrics scheduled (incomplete due to dry cracked skin)

February 6, 2013 - USPS Receipt/Delivered I-129F April 28, 2014 - Received Acceptance NOA1 hard copies for AOS and EAD May 13, 2016 - Walk in Biometrics Completed

February 8, 2013 - NOA1 Notice Date May 12, 2014 - Biometrics Appointment Done September 27, 2016 - ROC Approved (Checked status via website w/receipt #)

February 11, 2013 - Bank shows check cashed today May 15, 2014 - Interview Schedule Letter (received May 17, 2014) October 6, 2016 - Card Arrived

February 11, 2013 - E-Mail Notification of Case Acceptance and June 5, 2014 - Interview Scheduled at Local office 8:15 a.m.

Case Number (Routed to California Service Center) June 11, 2014 - USCIS Status updated to show Greencard in the mail

February 12, 2013 - E Mail Notification of Alien Registration Number Change w/USPS tracking showing it scheduled to arrive

February 15, 2013 - Hard Copy NOA1 received June 14, 2014

June 5, 2013 - Email notice of RFE June 13, 2014 - GreenCard arrived

June 6, 2013 - RFE postmarked

June 10, 2013 - RFE arrived in the mail

June 11, 2013 - RFE mailed back Express USPS

June 12, 2013 - RFE received @ CSC / USCIS website updated to reflect this

June 20, 2013 - I-129F Approved

June 24, 2013 - NOA2 Hard Copy Received

June 28, 2013 - NVC Assigned Case Number

July 2, 2013 - NVC shipped case to London

July 9, 2013 - London Received Case File

July 13, 2013 - Packet 3 Instructions Received

July 17, 2013 - Packet 3 Forms Mailed (Except DS-2001)

July 30, 2013 - DS-2001 sent (arrived July 31)

July 30, 2013 - Medical Scheduled (and completed w/no issues)

August 5th - Medical Results Logged in

August 8th - DS-2001 Logged in

August 20, 2013 - Interview Date Set

September 17, 2013 - Interview at 8:00 a.m. (APPROVED)

Waiting for VISA...

September 25, 2013 - Visa Delivered

October 8, 2013 - POE Las Vegas, NV

October 11, 2013 - Married

October 13th - HOME

Link to comment
Share on other sites

Filed: K-1 Visa Country: Philippines
Timeline

But they immediately refer to updating at or around the 15th of every month. This is using updating as the date the chart comes out.

Link to comment
Share on other sites

But they immediately refer to updating at or around the 15th of every month. This is using updating as the date the chart comes out.

your being way to technical on the wording. They update the page, but not the data. The data is updated as of the date listed on the page, which is January 31, 2013 right now

FILE FOR K-1 Adjustment of Status Removal of Conditions

January 31.2010 - Met Online April 10, 2014 - Mailed in I-485 + I-765 March 19, 2016 - Mailed I-751 to CSC

February 20, 2011 - Met in Person April 14, 2014 - Forms arrived at Chicago Lockbox March 23, 2016 - I-751 arrived at CSC

July 28, 2012 - Engaged April 17, 2014 - Acceptance email arrived stating case forwarded to NBC March 23, 2016 - NOA1 Date (received March 28)

February 5, 2013 - Mailed I-129F to Lewisville, TX April 27, 2014 - Received letter for Biometrics appointment April 20, 2016 - Biometrics scheduled (incomplete due to dry cracked skin)

February 6, 2013 - USPS Receipt/Delivered I-129F April 28, 2014 - Received Acceptance NOA1 hard copies for AOS and EAD May 13, 2016 - Walk in Biometrics Completed

February 8, 2013 - NOA1 Notice Date May 12, 2014 - Biometrics Appointment Done September 27, 2016 - ROC Approved (Checked status via website w/receipt #)

February 11, 2013 - Bank shows check cashed today May 15, 2014 - Interview Schedule Letter (received May 17, 2014) October 6, 2016 - Card Arrived

February 11, 2013 - E-Mail Notification of Case Acceptance and June 5, 2014 - Interview Scheduled at Local office 8:15 a.m.

Case Number (Routed to California Service Center) June 11, 2014 - USCIS Status updated to show Greencard in the mail

February 12, 2013 - E Mail Notification of Alien Registration Number Change w/USPS tracking showing it scheduled to arrive

February 15, 2013 - Hard Copy NOA1 received June 14, 2014

June 5, 2013 - Email notice of RFE June 13, 2014 - GreenCard arrived

June 6, 2013 - RFE postmarked

June 10, 2013 - RFE arrived in the mail

June 11, 2013 - RFE mailed back Express USPS

June 12, 2013 - RFE received @ CSC / USCIS website updated to reflect this

June 20, 2013 - I-129F Approved

June 24, 2013 - NOA2 Hard Copy Received

June 28, 2013 - NVC Assigned Case Number

July 2, 2013 - NVC shipped case to London

July 9, 2013 - London Received Case File

July 13, 2013 - Packet 3 Instructions Received

July 17, 2013 - Packet 3 Forms Mailed (Except DS-2001)

July 30, 2013 - DS-2001 sent (arrived July 31)

July 30, 2013 - Medical Scheduled (and completed w/no issues)

August 5th - Medical Results Logged in

August 8th - DS-2001 Logged in

August 20, 2013 - Interview Date Set

September 17, 2013 - Interview at 8:00 a.m. (APPROVED)

Waiting for VISA...

September 25, 2013 - Visa Delivered

October 8, 2013 - POE Las Vegas, NV

October 11, 2013 - Married

October 13th - HOME

Link to comment
Share on other sites

Filed: K-1 Visa Country: Philippines
Timeline

An "Update" can be made without necessarily reflecting any change in data.

02-27-2013 I-129F Packet Sent
03-03-2013 I-129F Packet Delivery
03-04-2013 NOA1 (text/email)
03-08-2013 A Number Changed
03-09-2013 Received NOA1 hardcopy
06-13-2013 Approved in 99 Days!
06-15-2013 Received NOA2 hardcopy
06-28-2013 Received MNL Case Number
07-08-2013 Manila Embassy Interview scheduled
07-22-2013 SLMEC Medical Exam Day 1
07-23-2013 SLMEC Medical Exam Day 2 - Passed!
08-31-2013 Arrived in Manila
09-02-2013 CFO - PASSED
09-03-2013 Manila Embassy Interview - APPROVED
09-05-2013 Visa Issued
09-09-2013 Visa ready for pick up at SM MOA
09-18-2013 Picked up passport and got CFO sticker

09-22-2013 Departed from Manila
10-04-2013 Fiancee departs for U.S.

Link to comment
Share on other sites

while VSC is back at 5 months ! So unfair... i am glad that my congressman got me through this and i ll have an answer within 30 days. Contact your representatives guys !

K1 Journey:

NOA1: 08/21/2012 (CSC)

NOA2: 04/24/2013 (8 months ClockWatch2.gif )

NVC received: 05/02/2013

NVC sent to Embassy: 05/06/2013 (only took 4 days !!)

Packet 3 received: 06/01/2013 (our son's 2nd birthday !!).Packet 3 response leaving in the mail on the next business day (06/04)

Medical: 06/11/2013

Interview: 06/18/2013. No packet 4 received, interview notice given on the phone the day before.

APPROVED !!

POE Chicago: 07/05/2013

AOS (EAD/AP) Journey:

NOA1: 07/30/2013

Biometrics: 09/09/2013

EAD/AP: 10/09/2013

Received a "potential interview waiver case" letter on 11/23/13.

GREEN CARD APPROVED AND IN PRODUCTION ON 03/17/2014

ROC I-751:

Sent: 01/09/16

NOA1: 01/11/16

Approval and Production Notice: 07/29/16

Link to comment
Share on other sites

Filed: K-1 Visa Country: Philippines
Timeline

That date is more of a cut off date, like they've processed 98% (I'm guessing) application processed before then and if you were earlier then you can file a service request.

Looking at Igor's list data, I agree. However, that is not what USCIS says in their table. I think they make it deliberately obtuse (so is it as of Jan 31, or March 22???), so they have the freedom to say what best benefits them, ie. less service requests/get the caller off the phone as soon as possible/screw you Jack.

Link to comment
Share on other sites

 
Didn't find the answer you were looking for? Ask our VJ Immigration Lawyers.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
- Back to Top -

Important Disclaimer: Please read carefully the Visajourney.com Terms of Service. If you do not agree to the Terms of Service you should not access or view any page (including this page) on VisaJourney.com. Answers and comments provided on Visajourney.com Forums are general information, and are not intended to substitute for informed professional medical, psychiatric, psychological, tax, legal, investment, accounting, or other professional advice. Visajourney.com does not endorse, and expressly disclaims liability for any product, manufacturer, distributor, service or service provider mentioned or any opinion expressed in answers or comments. VisaJourney.com does not condone immigration fraud in any way, shape or manner. VisaJourney.com recommends that if any member or user knows directly of someone involved in fraudulent or illegal activity, that they report such activity directly to the Department of Homeland Security, Immigration and Customs Enforcement. You can contact ICE via email at Immigration.Reply@dhs.gov or you can telephone ICE at 1-866-347-2423. All reported threads/posts containing reference to immigration fraud or illegal activities will be removed from this board. If you feel that you have found inappropriate content, please let us know by contacting us here with a url link to that content. Thank you.
×
×
  • Create New...