Jump to content
ny123

CR-1 process time?

 Share

8 posts in this topic

Recommended Posts

Filed: Country: China
Timeline

http://www.visajourney.com/content/ir1cr1historical

This page shows 4 steps for CR-1, the total of average process time in VSC is 5+105+74+10=204 days. But in the end it shows about 290 days is the total process time.

Do I miss anything? thanks.

Link to comment
Share on other sites

Filed: Citizen (apr) Country: India
Timeline

Add another 20 days for the time between USCIS Approval to case being received at NVC. Then add another 60 days between NVC case complete and Interview Date.

USA

01/08/13 - Approved and GC is order for production on 1/8/14

09/12/13 - Case transferred to CSC. NOA2 received on 09/18/13

08/30/13 - Biometrics Done - No walk ins allowed at this LSC (received on 8/16/13).

08/05/13 - NOA1 (received on 08/10/13)

08/01/13 - Mailed I-751 (received on 8/2/13 - check cashed on 8/5/13)

12/28/11 - Received SSN (applied on 12/20/11, as we didn't get based on DS-230 options)
11/28/11 - Received Green Card (Expires on 10/30/13) - Welcome Letter on 11/17/11
10/30/11 - POE - Houston, TX

Chennai Consulate (40 days)
10/28/11 - Received Visa papers and Passport at VFS
10/25/11 - Interview Cleared Successfully (Spouse was not allowed in)

NVC: (90 days from NOA2 to Consulate)
08/31/11 - Case Completed (Interview 10/25/11) - Received at Chennai on 09/19/11
07/22/11 - NVC Case Number

USCIS: (92 days)

6/21/11 - NOA2 (NOA1 on 3/25/11) - took a month to get to NVC
3/21/11 - I-130 sent to USCIS Lockbox, Chicago.

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: China
Timeline

ya, there are other timeticks for a CR-1 bound to Guangzhou, once USCIS/VSC has issued an approval:

Time Ticks for Tracking NVC EP Guangzhou - feel free to copy/paste this into yer profile/signature area/about me area:

NVC Received CaseFile *

NVC Casefile Number Issued *

Request DS-3032 Kit from NVC *

IIN received via email from NVC, as part of AOS Fee Bill EMAIL.

OPTIN EMAIL SENT TO NVC +

AOS FEE BILL PAID ONLINE &

AOS Fee Bill Marked Paid []

OPTIN ACCEPTED by NVC

AOS CoverSheets Generated &

IV Fee Bill Showing as 'Payable' []

IV FEE BILL PAID ONLINE &

IV Fee Bill marked as PAID []

IV CoverSheets Generated &

AOS email packet sent +

IV email packet sent +

NVC reports 'Case Completed' *

'Sign in Fail' at the Online Payment Portal &

Final Review Started at NVC *

Final Review Completed at NVC *

Interview Date Set *

Appointment Letter Received via Email

Interview Date

====

legend

* - USCitizen must call, inquire

+ - Your or foreign Spouse send off via email.

& - YOU do this.

[] - Online Payment Portal Status thingie - you log in, eyeball review it.

====

Things that go together -

OPT IN Accepted and IV Fee Bill Available to be Paid Online - almost the same date.

NVC Reports 'Case Complete' and 'Sign In Fail' - almost same day.

====

Things that make you go angly and aquiverish -

--Sign in Fail

--Final Review Complete (as Interview Date Set will occur within 6 days)

--Interview Date Set (time to get busy - you have between 20 to 45 days to wrap up yer relationship evidence)

====

A Note on Relationship Evidence for Guangzhou-bound petitions -

Please review this, send more if you must, during DS-230 submittal time -

http://www.visajourney.com/forums/topic/267559-usa-is-now-arizona/page__view__findpost__p__4100571

=--=-=-=-

IF YOU ARE NOT USING EP @NVC, ADD IN 2 TO 5 MONTHS OF DEAD ZONE TIME BETWEEN 'NVC OUT' AND GUZ IV OPEN CASEFILE, WITH ANOTHER 2 TO 3 MONTHS FOR SCHEDULING AND APPOINTMENT

Edited by Darnell

Sometimes my language usage seems confusing - please feel free to 'read it twice', just in case !
Ya know, you can find the answer to your question with the advanced search tool, when using a PC? Ditch the handphone, come back later on a PC, and try again.

-=-=-=-=-=R E A D ! ! !=-=-=-=-=-

Whoa Nelly ! Want NVC Info? see http://www.visajourney.com/wiki/index.php/NVC_Process

Congratulations on your approval ! We All Applaud your accomplishment with Most Wonderful Kissies !

 

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: China
Timeline

ya, sorry, people view immigration as a right, and it's not.

It's a priviledge, instead. Long standing argument here at VJ about it, as well.

You do have a right to fill out the forms properly, however - VJ can be useful in that, if you study the guides.

IMO, it's good to be scared - GUZ IV is one of the toughest IV units in the world, high fraud area. Being forewarned helps you to be fore-armed, but it's up to you to handle all.

Edited by Darnell

Sometimes my language usage seems confusing - please feel free to 'read it twice', just in case !
Ya know, you can find the answer to your question with the advanced search tool, when using a PC? Ditch the handphone, come back later on a PC, and try again.

-=-=-=-=-=R E A D ! ! !=-=-=-=-=-

Whoa Nelly ! Want NVC Info? see http://www.visajourney.com/wiki/index.php/NVC_Process

Congratulations on your approval ! We All Applaud your accomplishment with Most Wonderful Kissies !

 

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: China
Timeline

What is really important, is to get the process done right the first time.

It takes alot of research to guess what the real requirements are at Guangzhou...

April 2008 Met online ..................... March 2010.. 3 week visit......... 19 Nov...Sent DS230 & I-864

April 2009 Met in Chongqing .......... 09 March 2010 .. Marry.................17Dec...NVC lost 230 and 864

04 May 09 Apply K1 .................... 10 April .. Apply CR1....................20Dec..NVC found 230

18 May 09 NOA 1......................... 20 April... NOA1...........................28Dec..sent more 864 docs

16 Sep 09 NOA 2......................... 06 Oct..... NOA2...........................2011

08 Nov 09 P3................................... 21 Oct..... Have Case #..............21 Jan...SIF

06 Dec 09 P4............................... 30 OCt..... Have DS-3032...............26 Jan .. CC

29 Dec 09. Interview..................... 1 Nov..... email Ds-3032...............1 Apr, 3 week visit

29 Dec,,,,No Visa.......................... 1 Nov......paid AOS.......................4 May Interview.Approved..

9 Aug 2010 I-129F ended.............. 5 Nov......paid IV.........,,,,,,,,,,, ..... 28 June, Received Visa

............................................................................................................22 July, arrive USA..

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: China
Timeline

[pumps fist in air- research rocks!!! ]

Sometimes my language usage seems confusing - please feel free to 'read it twice', just in case !
Ya know, you can find the answer to your question with the advanced search tool, when using a PC? Ditch the handphone, come back later on a PC, and try again.

-=-=-=-=-=R E A D ! ! !=-=-=-=-=-

Whoa Nelly ! Want NVC Info? see http://www.visajourney.com/wiki/index.php/NVC_Process

Congratulations on your approval ! We All Applaud your accomplishment with Most Wonderful Kissies !

 

Link to comment
Share on other sites

 
Didn't find the answer you were looking for? Ask our VJ Immigration Lawyers.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
- Back to Top -

Important Disclaimer: Please read carefully the Visajourney.com Terms of Service. If you do not agree to the Terms of Service you should not access or view any page (including this page) on VisaJourney.com. Answers and comments provided on Visajourney.com Forums are general information, and are not intended to substitute for informed professional medical, psychiatric, psychological, tax, legal, investment, accounting, or other professional advice. Visajourney.com does not endorse, and expressly disclaims liability for any product, manufacturer, distributor, service or service provider mentioned or any opinion expressed in answers or comments. VisaJourney.com does not condone immigration fraud in any way, shape or manner. VisaJourney.com recommends that if any member or user knows directly of someone involved in fraudulent or illegal activity, that they report such activity directly to the Department of Homeland Security, Immigration and Customs Enforcement. You can contact ICE via email at Immigration.Reply@dhs.gov or you can telephone ICE at 1-866-347-2423. All reported threads/posts containing reference to immigration fraud or illegal activities will be removed from this board. If you feel that you have found inappropriate content, please let us know by contacting us here with a url link to that content. Thank you.
×
×
  • Create New...