Filed: Lift. Cond. (apr) Country: China
Timeline

I received an email yesterday with case status: Post Decision Activity

Today, I received another email with case status: Acceptance

Yesterday:

Application Type: I129F , PETITION FOR FIANCE(E)

Your Case Status: Post Decision Activity

On May 19, 2011, we mailed you a notice that we have approved this I129F PETITION FOR FIANCE(E). Please follow any instructions on the notice. If you move before you receive the notice, call customer service at 1-800-375-5283.

Today:

Application Type: I129F , PETITION FOR FIANCE(E)

Your Case Status: Acceptance

On May 20, 2011, a duplicate notice was mailed to you regarding a decision on this case, or describing how we will process the case if it is still pending. Please follow any instructions on the notice. Your case is at our VERMONT SERVICE CENTER location. If this I129F, PETITION FOR FIANCE(E) is still pending, you will be notified by mail when a decision is made, or if the office needs something from you. If you move and this case is still pending, please use our Change of Address online tool to update your case with your new address or call our customer service center at 1-800-375-5283.

During the acceptance step USCIS reviews newly received applications and petitions to ensure that they are properly filed (i.e. signed by the applicant, appropriate fees, etc.) USCIS issues a receipt number for the application or petition, and sends a receipt notice to the applicant or petitioner.

Applications and petitions that are not properly filed are rejected with an explanation of why the application is rejected and the corrective action needed. Rejected applications or petitions do not retain their filing date.

The acceptance step is typically completed within 2 business days of when the application is received. With mail time it may take several weeks for you to get the receipt or rejection notice in the mail. If you do not receive your notice within 30 days of mailing your application, please contact our national customer service center at 1-800-375-5283.

I called USCIS, got a human, and she simply read me the same script and then told me no one else can give me anymore information regarding my case. She said the only way to reach VSC is to write to them.

Any ideas?

Thanks :)

ROC

2014-05-17 (Sat) Card Received! Text and email: "The USPS reported that your new card was delivered on May 17, 2014"

2014-05-15 (Thurs) Received "USPS picked up mail from USCIS" text and email

2014-05-15 (Thurs) Received "card mailed" text and email

2014-05-14 (Wed) Received "card production" text and email

2014-05-12 (Mon) Received approval letter

2014-05-08 (Thurs) Date of Decision - Approved!

2013-11-29 (Fri) Early Biometrics done on Black Friday

2013-11-18 (Mon) Received Biometrics Appointment letter for 12/04/13

2013-11-09 (Sat) NOA1 Hardcopy

2013-11-08 (Fri) Check cashed

2013-11-06 (Wed) NOA1 Receipt Date

2013-11-04 (Mon) Mailed ROC Package

AOS

2012-02-11 (Sat) Green Card arrived!!

2012-02-09 (Thurs) Received Permanent Resident Welcome Letter

2012-02-07 (Tues) 12:45am I-485 Card Production (ordered production)

2012-02-06 (Mon) 6:45pm I-485 Decision (registered PR status)

2012-02-06 (Mon) 3:00pm I-485 Card Production (ordered production)

2011-12-08 (Thurs) Received EAD/AP combo card

2011-11-30 (Wed) Email/text: I-131(AP) approved. I-765(EAD) card production.

2011-10-25 (Tues) Completed biometrics

2011-10-21 (Fri) I-485 case transferred

2011-10-10 (Tues) Two NOA's: I-485 and I-765 payment receipts. Notice date 10/03/11

2011-10-08 (Sat) Biometrics Appointment letter for 10/25/11

2011-10-04 (Tues) Check cashed.

2011-10-03 (Mon) NOA's for I-485, I-131, and I-765

2011-09-30 (Fri) USCIS web status shows receipt for I-485, I-131, and I-765

2011-09-29 (Thurs) USPS delivery confirmation

2011-09-27 (Tues) Mailed AOS package

k-1

2011-07-25 (Mon) Visa in hand!!

2011-07-19 (Tue) Interview at 7:30am - Approved!!

2011-07-18 (Mon) Document in-take at 12:30pm

2011-05-19 (Thu) NOA2 (160 days from NOA1)

2010-12-15 (Wed) NOA1 hard copy received

2010-12-09 (Thu) I-129F package arrived USCIS PO Box in Dallas

2010-12-07 (Tue) Mailed I-129F package

Link to comment
Share on other sites

Filed: Lift. Cond. (apr) Country: China
Timeline

You should get the notice in the mail in a couple of days. I wouldn't put too much into the status on the website or what the operator told you.

Thanks for your prompt reply. It's just weird. Both notices came via email and text message, and then I checked online before calling USCIS customer service.

I was afraid it's one of those decision reversal deals: someone changed their mind after the petition was approved.

Or, a data entry person had a typo when entering my case number or someone else's case number.

I guess I'll just have to wait for the hard copies to know for sure :)

ROC

2014-05-17 (Sat) Card Received! Text and email: "The USPS reported that your new card was delivered on May 17, 2014"

2014-05-15 (Thurs) Received "USPS picked up mail from USCIS" text and email

2014-05-15 (Thurs) Received "card mailed" text and email

2014-05-14 (Wed) Received "card production" text and email

2014-05-12 (Mon) Received approval letter

2014-05-08 (Thurs) Date of Decision - Approved!

2013-11-29 (Fri) Early Biometrics done on Black Friday

2013-11-18 (Mon) Received Biometrics Appointment letter for 12/04/13

2013-11-09 (Sat) NOA1 Hardcopy

2013-11-08 (Fri) Check cashed

2013-11-06 (Wed) NOA1 Receipt Date

2013-11-04 (Mon) Mailed ROC Package

AOS

2012-02-11 (Sat) Green Card arrived!!

2012-02-09 (Thurs) Received Permanent Resident Welcome Letter

2012-02-07 (Tues) 12:45am I-485 Card Production (ordered production)

2012-02-06 (Mon) 6:45pm I-485 Decision (registered PR status)

2012-02-06 (Mon) 3:00pm I-485 Card Production (ordered production)

2011-12-08 (Thurs) Received EAD/AP combo card

2011-11-30 (Wed) Email/text: I-131(AP) approved. I-765(EAD) card production.

2011-10-25 (Tues) Completed biometrics

2011-10-21 (Fri) I-485 case transferred

2011-10-10 (Tues) Two NOA's: I-485 and I-765 payment receipts. Notice date 10/03/11

2011-10-08 (Sat) Biometrics Appointment letter for 10/25/11

2011-10-04 (Tues) Check cashed.

2011-10-03 (Mon) NOA's for I-485, I-131, and I-765

2011-09-30 (Fri) USCIS web status shows receipt for I-485, I-131, and I-765

2011-09-29 (Thurs) USPS delivery confirmation

2011-09-27 (Tues) Mailed AOS package

k-1

2011-07-25 (Mon) Visa in hand!!

2011-07-19 (Tue) Interview at 7:30am - Approved!!

2011-07-18 (Mon) Document in-take at 12:30pm

2011-05-19 (Thu) NOA2 (160 days from NOA1)

2010-12-15 (Wed) NOA1 hard copy received

2010-12-09 (Thu) I-129F package arrived USCIS PO Box in Dallas

2010-12-07 (Tue) Mailed I-129F package

Link to comment
Share on other sites

Filed: Lift. Cond. (apr) Country: China
Timeline

Hi, Looks like you have good news coming soon, much luck to you :)

Thank you, I do hope it's good news in duplicate :)

It's strange to see the 4th circle on the website one day and back to the 1st circle the next. Kind of like, "you passed! ..... just kidding" :)

ROC

2014-05-17 (Sat) Card Received! Text and email: "The USPS reported that your new card was delivered on May 17, 2014"

2014-05-15 (Thurs) Received "USPS picked up mail from USCIS" text and email

2014-05-15 (Thurs) Received "card mailed" text and email

2014-05-14 (Wed) Received "card production" text and email

2014-05-12 (Mon) Received approval letter

2014-05-08 (Thurs) Date of Decision - Approved!

2013-11-29 (Fri) Early Biometrics done on Black Friday

2013-11-18 (Mon) Received Biometrics Appointment letter for 12/04/13

2013-11-09 (Sat) NOA1 Hardcopy

2013-11-08 (Fri) Check cashed

2013-11-06 (Wed) NOA1 Receipt Date

2013-11-04 (Mon) Mailed ROC Package

AOS

2012-02-11 (Sat) Green Card arrived!!

2012-02-09 (Thurs) Received Permanent Resident Welcome Letter

2012-02-07 (Tues) 12:45am I-485 Card Production (ordered production)

2012-02-06 (Mon) 6:45pm I-485 Decision (registered PR status)

2012-02-06 (Mon) 3:00pm I-485 Card Production (ordered production)

2011-12-08 (Thurs) Received EAD/AP combo card

2011-11-30 (Wed) Email/text: I-131(AP) approved. I-765(EAD) card production.

2011-10-25 (Tues) Completed biometrics

2011-10-21 (Fri) I-485 case transferred

2011-10-10 (Tues) Two NOA's: I-485 and I-765 payment receipts. Notice date 10/03/11

2011-10-08 (Sat) Biometrics Appointment letter for 10/25/11

2011-10-04 (Tues) Check cashed.

2011-10-03 (Mon) NOA's for I-485, I-131, and I-765

2011-09-30 (Fri) USCIS web status shows receipt for I-485, I-131, and I-765

2011-09-29 (Thurs) USPS delivery confirmation

2011-09-27 (Tues) Mailed AOS package

k-1

2011-07-25 (Mon) Visa in hand!!

2011-07-19 (Tue) Interview at 7:30am - Approved!!

2011-07-18 (Mon) Document in-take at 12:30pm

2011-05-19 (Thu) NOA2 (160 days from NOA1)

2010-12-15 (Wed) NOA1 hard copy received

2010-12-09 (Thu) I-129F package arrived USCIS PO Box in Dallas

2010-12-07 (Tue) Mailed I-129F package

Link to comment
Share on other sites

Filed: Lift. Cond. (apr) Country: China
Timeline

Update:

I called USCIS again this afternoon, and got escalated to someone who could tell me something.

She said their computer system has been having problems lately :D

As far as she can tell, my petition has not been approved :D Great!!

She told me to call back sometime next week to see if their system gets an update with the correct status.

Well, looks like I'm the first one at VJ to be experiencing this. I guess I shouldn't have celebrated until I received the NOA2 in the mail :D

ROC

2014-05-17 (Sat) Card Received! Text and email: "The USPS reported that your new card was delivered on May 17, 2014"

2014-05-15 (Thurs) Received "USPS picked up mail from USCIS" text and email

2014-05-15 (Thurs) Received "card mailed" text and email

2014-05-14 (Wed) Received "card production" text and email

2014-05-12 (Mon) Received approval letter

2014-05-08 (Thurs) Date of Decision - Approved!

2013-11-29 (Fri) Early Biometrics done on Black Friday

2013-11-18 (Mon) Received Biometrics Appointment letter for 12/04/13

2013-11-09 (Sat) NOA1 Hardcopy

2013-11-08 (Fri) Check cashed

2013-11-06 (Wed) NOA1 Receipt Date

2013-11-04 (Mon) Mailed ROC Package

AOS

2012-02-11 (Sat) Green Card arrived!!

2012-02-09 (Thurs) Received Permanent Resident Welcome Letter

2012-02-07 (Tues) 12:45am I-485 Card Production (ordered production)

2012-02-06 (Mon) 6:45pm I-485 Decision (registered PR status)

2012-02-06 (Mon) 3:00pm I-485 Card Production (ordered production)

2011-12-08 (Thurs) Received EAD/AP combo card

2011-11-30 (Wed) Email/text: I-131(AP) approved. I-765(EAD) card production.

2011-10-25 (Tues) Completed biometrics

2011-10-21 (Fri) I-485 case transferred

2011-10-10 (Tues) Two NOA's: I-485 and I-765 payment receipts. Notice date 10/03/11

2011-10-08 (Sat) Biometrics Appointment letter for 10/25/11

2011-10-04 (Tues) Check cashed.

2011-10-03 (Mon) NOA's for I-485, I-131, and I-765

2011-09-30 (Fri) USCIS web status shows receipt for I-485, I-131, and I-765

2011-09-29 (Thurs) USPS delivery confirmation

2011-09-27 (Tues) Mailed AOS package

k-1

2011-07-25 (Mon) Visa in hand!!

2011-07-19 (Tue) Interview at 7:30am - Approved!!

2011-07-18 (Mon) Document in-take at 12:30pm

2011-05-19 (Thu) NOA2 (160 days from NOA1)

2010-12-15 (Wed) NOA1 hard copy received

2010-12-09 (Thu) I-129F package arrived USCIS PO Box in Dallas

2010-12-07 (Tue) Mailed I-129F package

Link to comment
Share on other sites

:thumbs::dance: :dance: :thumbs:
N-400:
May 9, 2017: N-400 packet was sent
May 15, 2017: NOA1 
June 05, 2017: Biometric Done
June 19, 2017: Case is in Line for an Interview
June 25, 2018: USCIS Scheduled an Interview
Aug. 02, 2018: Interview Date- APPROVED!
Aug. 09, 2018: Oath Ceremony

My Group

My Blog

Link to comment
Share on other sites

Filed: Citizen (apr) Country: Canada
Timeline

Sounds good! Congratulations. kicking.gif

USCIS

NOA1 08/19/08

NOA2 01/20/09

NVC

Received 01/26/09

Completed 02/13/09 (19 Days)

Interview Assigned 03/27/09 (6 weeks after NVC completion)

Medical

04/14/09 (Toronto)

Interview

Montreal 05/12/09 (88 days after NVC completion) **APPROVED**

POE

06/16/09 Buffalo

07/02/09 Welcome Letter Received

07/07/09 Applied for SSN

07/10/09 "Card production ordered" email received

07/13/09 SSN received

07/14/09 "Approval notice sent" email received

07/17/09 GREEN CARD received

Removal of Conditions

03/21/11 I-751 mailed to VSC

03/23/11 I-751 received at VSC

03/29/11 Cheque Cashed

03/30/11 NOA1 received (3/24/11)

04/11/11 Biometrics appointment notice received

05/05/11 Biometric appointment

12/13/11 **Approval date** (5 days short of 9 months!)

12/19/11 Approval letter and green card received

Naturalization

05/16/2019 Filed online (estimated completion February 2020)

05/18/2019 Biometrics scheduled

05/21/2019 Receipt notice and biometrics notices posted to online account.05/23/2019 Hard copy of NOA1 received

05/24/2019 Hard copy of biometrics appointment received

06/07/2019 Biometrics appointment (estimated completion January 2020)

12/31/2019 Email received "Interview scheduled"

01/01/2020 Interview date notice posted to online account (02/19/2020)

01/05/2019 Hard copy of interview appointment received

02/19/2020 Interview (**Approved**) and same day Oath Ceremony. 

Link to comment
Share on other sites

System error... darn, that stinks. Sorry to hear you have to deal with this, and I hope they fix it quickly so others aren't teased in the same manner.

May your real approval come quickly in spite of this hiccup - all the best.

2-11-11 | I-129F sent

2-16-11 | NOA1

6-06-11 | NOA2

Link to comment
Share on other sites

Filed: Lift. Cond. (apr) Country: China
Timeline

System error... darn, that stinks. Sorry to hear you have to deal with this, and I hope they fix it quickly so others aren't teased in the same manner.

May your real approval come quickly in spite of this hiccup - all the best.

Yes, this kind of system error is nerve-wracking and emotionally devastating to say the least. It's also a very cruel joke :D

Thank you for your well wishes. My fiancee and I are looking at the positive side, believing in the first email and ignoring the second.

Hopefully we'll get our approval letter in the mail soon.

I'm glad the tier 2 rep at USCIS told me to call back next week instead of 30 days later. She is well aware that this is a problem with their system because she couldn't give me anymore info besides what the computer told her yesterday. I'll be calling USCIS next week until I get a satisfactory answer and will post my findings here :)

Have a great weekend!

ROC

2014-05-17 (Sat) Card Received! Text and email: "The USPS reported that your new card was delivered on May 17, 2014"

2014-05-15 (Thurs) Received "USPS picked up mail from USCIS" text and email

2014-05-15 (Thurs) Received "card mailed" text and email

2014-05-14 (Wed) Received "card production" text and email

2014-05-12 (Mon) Received approval letter

2014-05-08 (Thurs) Date of Decision - Approved!

2013-11-29 (Fri) Early Biometrics done on Black Friday

2013-11-18 (Mon) Received Biometrics Appointment letter for 12/04/13

2013-11-09 (Sat) NOA1 Hardcopy

2013-11-08 (Fri) Check cashed

2013-11-06 (Wed) NOA1 Receipt Date

2013-11-04 (Mon) Mailed ROC Package

AOS

2012-02-11 (Sat) Green Card arrived!!

2012-02-09 (Thurs) Received Permanent Resident Welcome Letter

2012-02-07 (Tues) 12:45am I-485 Card Production (ordered production)

2012-02-06 (Mon) 6:45pm I-485 Decision (registered PR status)

2012-02-06 (Mon) 3:00pm I-485 Card Production (ordered production)

2011-12-08 (Thurs) Received EAD/AP combo card

2011-11-30 (Wed) Email/text: I-131(AP) approved. I-765(EAD) card production.

2011-10-25 (Tues) Completed biometrics

2011-10-21 (Fri) I-485 case transferred

2011-10-10 (Tues) Two NOA's: I-485 and I-765 payment receipts. Notice date 10/03/11

2011-10-08 (Sat) Biometrics Appointment letter for 10/25/11

2011-10-04 (Tues) Check cashed.

2011-10-03 (Mon) NOA's for I-485, I-131, and I-765

2011-09-30 (Fri) USCIS web status shows receipt for I-485, I-131, and I-765

2011-09-29 (Thurs) USPS delivery confirmation

2011-09-27 (Tues) Mailed AOS package

k-1

2011-07-25 (Mon) Visa in hand!!

2011-07-19 (Tue) Interview at 7:30am - Approved!!

2011-07-18 (Mon) Document in-take at 12:30pm

2011-05-19 (Thu) NOA2 (160 days from NOA1)

2010-12-15 (Wed) NOA1 hard copy received

2010-12-09 (Thu) I-129F package arrived USCIS PO Box in Dallas

2010-12-07 (Tue) Mailed I-129F package

Link to comment
Share on other sites

Filed: Lift. Cond. (apr) Country: China
Timeline

did you get email or text from USCIS of approval?

I got both text message and email both days :)

The text messages said my case was updated. Exactly 2 minutes later, I received the email. I posted the main part of my emails word-for-word in the original post above.

I tried to figure out if they sent me two approval NOA2's in the mail or if they decided they need more time to process my case. Either way, I can't see my case being kicked back to step 1 (Acceptance). I couldn't figure out, so I called USCIS. It didn't take me long at all to speak to a person on Friday. All she (tier 2) could tell from her screen was that my petition hasn't been adjudicated :D

So, did you get an email and text message too? Looks like you were approved a day before me, and I assume you have not received your approval in the mail. Let's hope our letters come soon so we can move on :)

ROC

2014-05-17 (Sat) Card Received! Text and email: "The USPS reported that your new card was delivered on May 17, 2014"

2014-05-15 (Thurs) Received "USPS picked up mail from USCIS" text and email

2014-05-15 (Thurs) Received "card mailed" text and email

2014-05-14 (Wed) Received "card production" text and email

2014-05-12 (Mon) Received approval letter

2014-05-08 (Thurs) Date of Decision - Approved!

2013-11-29 (Fri) Early Biometrics done on Black Friday

2013-11-18 (Mon) Received Biometrics Appointment letter for 12/04/13

2013-11-09 (Sat) NOA1 Hardcopy

2013-11-08 (Fri) Check cashed

2013-11-06 (Wed) NOA1 Receipt Date

2013-11-04 (Mon) Mailed ROC Package

AOS

2012-02-11 (Sat) Green Card arrived!!

2012-02-09 (Thurs) Received Permanent Resident Welcome Letter

2012-02-07 (Tues) 12:45am I-485 Card Production (ordered production)

2012-02-06 (Mon) 6:45pm I-485 Decision (registered PR status)

2012-02-06 (Mon) 3:00pm I-485 Card Production (ordered production)

2011-12-08 (Thurs) Received EAD/AP combo card

2011-11-30 (Wed) Email/text: I-131(AP) approved. I-765(EAD) card production.

2011-10-25 (Tues) Completed biometrics

2011-10-21 (Fri) I-485 case transferred

2011-10-10 (Tues) Two NOA's: I-485 and I-765 payment receipts. Notice date 10/03/11

2011-10-08 (Sat) Biometrics Appointment letter for 10/25/11

2011-10-04 (Tues) Check cashed.

2011-10-03 (Mon) NOA's for I-485, I-131, and I-765

2011-09-30 (Fri) USCIS web status shows receipt for I-485, I-131, and I-765

2011-09-29 (Thurs) USPS delivery confirmation

2011-09-27 (Tues) Mailed AOS package

k-1

2011-07-25 (Mon) Visa in hand!!

2011-07-19 (Tue) Interview at 7:30am - Approved!!

2011-07-18 (Mon) Document in-take at 12:30pm

2011-05-19 (Thu) NOA2 (160 days from NOA1)

2010-12-15 (Wed) NOA1 hard copy received

2010-12-09 (Thu) I-129F package arrived USCIS PO Box in Dallas

2010-12-07 (Tue) Mailed I-129F package

Link to comment
Share on other sites

Filed: Timeline

I got both text message and email both days :)

The text messages said my case was updated. Exactly 2 minutes later, I received the email. I posted the main part of my emails word-for-word in the original post above.

I tried to figure out if they sent me two approval NOA2's in the mail or if they decided they need more time to process my case. Either way, I can't see my case being kicked back to step 1 (Acceptance). I couldn't figure out, so I called USCIS. It didn't take me long at all to speak to a person on Friday. All she (tier 2) could tell from her screen was that my petition hasn't been adjudicated :D

So, did you get an email and text message too? Looks like you were approved a day before me, and I assume you have not received your approval in the mail. Let's hope our letters come soon so we can move on :)

yeah you are right..we haven't get any email or text for approval...just in USCIS site.. since i read your post,i can't help checking and checking the USCIS site :wacko:

keep on praying.. we will be fine and soon this will be over and live life together with our love ones happily ever after... :thumbs:

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: Turkey
Timeline

I received an email yesterday with case status: Post Decision Activity

Today, I received another email with case status: Acceptance

Yesterday:

Application Type: I129F , PETITION FOR FIANCE(E)

Your Case Status: Post Decision Activity

On May 19, 2011, we mailed you a notice that we have approved this I129F PETITION FOR FIANCE(E). Please follow any instructions on the notice. If you move before you receive the notice, call customer service at 1-800-375-5283.

Today:

Application Type: I129F , PETITION FOR FIANCE(E)

Your Case Status: Acceptance

On May 20, 2011, a duplicate notice was mailed to you regarding a decision on this case, or describing how we will process the case if it is still pending. Please follow any instructions on the notice. Your case is at our VERMONT SERVICE CENTER location. If this I129F, PETITION FOR FIANCE(E) is still pending, you will be notified by mail when a decision is made, or if the office needs something from you. If you move and this case is still pending, please use our Change of Address online tool to update your case with your new address or call our customer service center at 1-800-375-5283.

During the acceptance step USCIS reviews newly received applications and petitions to ensure that they are properly filed (i.e. signed by the applicant, appropriate fees, etc.) USCIS issues a receipt number for the application or petition, and sends a receipt notice to the applicant or petitioner.

Applications and petitions that are not properly filed are rejected with an explanation of why the application is rejected and the corrective action needed. Rejected applications or petitions do not retain their filing date.

The acceptance step is typically completed within 2 business days of when the application is received. With mail time it may take several weeks for you to get the receipt or rejection notice in the mail. If you do not receive your notice within 30 days of mailing your application, please contact our national customer service center at 1-800-375-5283.

I called USCIS, got a human, and she simply read me the same script and then told me no one else can give me anymore information regarding my case. She said the only way to reach VSC is to write to them.

Any ideas?

Thanks :)

This is basically just the e-mail acceptance and you will get the actual "paper letter" of acceptance within a few days. I got mine 3 days later. Then wait about 5 days and call NVC 603-334-0700 and ask them for your NVC case #. Then it takes on average 20-30 days (depending on processing time) before it is sent to consulate. Normally it is sent to consulate and received within 3-5 business days after that! Hope this helps

event.png

Tuana and Kemal's Visa Journey

2010.07.10 We met

2010.10.28 First visit to meet in person

2010.10.31 We became engaged

2011.01.12 Second Visit with my Husband

2011.04.18 Third Visit with my Husband

2011.08.19 Married in Gaziantep Turkey, 4th Visit

2011.10.21 Visited with my Husband, 5th Visit

2011.11.22 SENT IN I-130 Application

2011.12.01 NOA1 Received

2012.02.16 Visited my Husband, 6th Visit

2012.05.08 NOA2 Received

2012.05.21 NVC Received

2012.07.02 Per NVC documents approved, waiting on interview date to be scheduled

2012.08.10 Visited my husband in Turkey, 7th Visit

2012.12.04 Visa Approved

Link to comment
Share on other sites

Filed: Lift. Cond. (apr) Country: China
Timeline

This is basically just the e-mail acceptance and you will get the actual "paper letter" of acceptance within a few days. I got mine 3 days later. Then wait about 5 days and call NVC 603-334-0700 and ask them for your NVC case #. Then it takes on average 20-30 days (depending on processing time) before it is sent to consulate. Normally it is sent to consulate and received within 3-5 business days after that! Hope this helps

Kemal and Tuana,

That helps a lot if you are confirming what you got is what I got :)

I've never heard or read of anyone else at VJ receiving 2 emails in 2 days.

Are you saying that my first email was for "petition approved at VSC" and my second email says "accepted at NVC"?

So, in your case, you got an "NOA2 letter" and an "acceptance letter" in the mail a few days after you got those 2 emails?

I'm still a little confused as to what "acceptance" means: accepted by whom and for what, since the petition was accepted back in December 2010 and supposedly processed and approved a few days ago :)

Thanks once again for sharing your experience!! :)

ROC

2014-05-17 (Sat) Card Received! Text and email: "The USPS reported that your new card was delivered on May 17, 2014"

2014-05-15 (Thurs) Received "USPS picked up mail from USCIS" text and email

2014-05-15 (Thurs) Received "card mailed" text and email

2014-05-14 (Wed) Received "card production" text and email

2014-05-12 (Mon) Received approval letter

2014-05-08 (Thurs) Date of Decision - Approved!

2013-11-29 (Fri) Early Biometrics done on Black Friday

2013-11-18 (Mon) Received Biometrics Appointment letter for 12/04/13

2013-11-09 (Sat) NOA1 Hardcopy

2013-11-08 (Fri) Check cashed

2013-11-06 (Wed) NOA1 Receipt Date

2013-11-04 (Mon) Mailed ROC Package

AOS

2012-02-11 (Sat) Green Card arrived!!

2012-02-09 (Thurs) Received Permanent Resident Welcome Letter

2012-02-07 (Tues) 12:45am I-485 Card Production (ordered production)

2012-02-06 (Mon) 6:45pm I-485 Decision (registered PR status)

2012-02-06 (Mon) 3:00pm I-485 Card Production (ordered production)

2011-12-08 (Thurs) Received EAD/AP combo card

2011-11-30 (Wed) Email/text: I-131(AP) approved. I-765(EAD) card production.

2011-10-25 (Tues) Completed biometrics

2011-10-21 (Fri) I-485 case transferred

2011-10-10 (Tues) Two NOA's: I-485 and I-765 payment receipts. Notice date 10/03/11

2011-10-08 (Sat) Biometrics Appointment letter for 10/25/11

2011-10-04 (Tues) Check cashed.

2011-10-03 (Mon) NOA's for I-485, I-131, and I-765

2011-09-30 (Fri) USCIS web status shows receipt for I-485, I-131, and I-765

2011-09-29 (Thurs) USPS delivery confirmation

2011-09-27 (Tues) Mailed AOS package

k-1

2011-07-25 (Mon) Visa in hand!!

2011-07-19 (Tue) Interview at 7:30am - Approved!!

2011-07-18 (Mon) Document in-take at 12:30pm

2011-05-19 (Thu) NOA2 (160 days from NOA1)

2010-12-15 (Wed) NOA1 hard copy received

2010-12-09 (Thu) I-129F package arrived USCIS PO Box in Dallas

2010-12-07 (Tue) Mailed I-129F package

Link to comment
Share on other sites

 
Didn't find the answer you were looking for? Ask our VJ Immigration Lawyers.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
- Back to Top -

Important Disclaimer: Please read carefully the Visajourney.com Terms of Service. If you do not agree to the Terms of Service you should not access or view any page (including this page) on VisaJourney.com. Answers and comments provided on Visajourney.com Forums are general information, and are not intended to substitute for informed professional medical, psychiatric, psychological, tax, legal, investment, accounting, or other professional advice. Visajourney.com does not endorse, and expressly disclaims liability for any product, manufacturer, distributor, service or service provider mentioned or any opinion expressed in answers or comments. VisaJourney.com does not condone immigration fraud in any way, shape or manner. VisaJourney.com recommends that if any member or user knows directly of someone involved in fraudulent or illegal activity, that they report such activity directly to the Department of Homeland Security, Immigration and Customs Enforcement. You can contact ICE via email at Immigration.Reply@dhs.gov or you can telephone ICE at 1-866-347-2423. All reported threads/posts containing reference to immigration fraud or illegal activities will be removed from this board. If you feel that you have found inappropriate content, please let us know by contacting us here with a url link to that content. Thank you.
×
×
  • Create New...